It looks like dredging is on track to begin later this month. This means the actual dredging itself. Right now, the plan is to start in the inside channel from the Rescue dock through the mouth of the marina. This will mean there will be some closure times where boats will not be able to get out on the lake. We are working on a plan to minimize closure times. The rough estimate is it will take about two weeks to complete this area. We do anticipate closures to only be the length of hours rather than days though. Updates on dredging activity will become more frequent now. Dave Shearer Harbor Master Great Salt Lake State Marina Antelope Island State Marina 801-209-9142