CRANE USERS-
FRIDAY OCTOBER 5TH 12 NOON IS THE DAY SELECTED.
Due to the weight of Jeanne’s Tarten we will need the 130 ton crane – the reach will be 100 to 120 ft – the crane is good for 12,600 lbs at 100 ft reach.
We need to have Dave Shearer confirm the reach based on the slip we will use
The estimated cost is as follows; please note that the key to only using the crane for 4 or 5 hours is our preparedness. 6 boats is actually very affordable, more than 6 boats doesn’t always translate to lower costs. Travel time is included in the hour totals so 3 hours /6 boats allow 30 minutes per boat plus 2 hours travel
4 hours x 260 per hour = $1040.00 / 6 boats = $ 173.30 each
5 hours x 260 per hour = $ 1300.00 / 6 boats = $ 216.66 each
6 hours x 260 per hour = $ 1560.00 / 6 boats = $ 260.00 each
PLEASE SEND A CHECK FOR $ 260.00 TO ME BY SATURDAY THE 29TH. It will need to be in the mail soon. ; This allows me time to cancel the crane if all the deposits are not received. I will give back what we don’t use. Include your return address and phone # please. IF $260.00 is too much please let me know as soon as possible. I believe that $ 215.00 will be the actual cost if all 6 boats show up. ONCE AGAIN THIS IS A USE IT OR LOSE USE IT DEPOSIT – NO REFUNDS. Please bring a check book just incase we have a problem.
BRIAN BALES
135 CRESTVIEW CIRCLE
PARK CITY, UTAH 84098
FINAL LIST to DATE – please inform me if you are not going to use the crane.
David- 263-3045 H- 230-3539 CELL Olsen 30
Brian – 455-4434 wilderness 30.
Judy hunter 25.5
Todd Daniel Catalina 26
Jeanne Ware Tarten 9000 lbs 897-8645 / 916-7687 / 447-4115
Dale Clark 726-5308 Ericson 26 NEEDS TO CONFIRM. !!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!
POSSIBLES
Kathy Berrett
Craig Brown- 554-5519 carpe diem 27 - needs trailer
Thank you,
Brian Bales
estimator / project manager
_______________________________________________
GSL-Marina mailing list
GSL-Marina@mailman.xmission.com
http://mailman.xmission.com/cgi-bin/mailman/listinfo/gsl-marina